苦等三年,建筑股依然冷飕飕;
真让人心寒
Eddy Gan
Share price continue low as long as THE PEAK condominium project problem not able to resolve & company need to pay LAD to buyers RM 15 million per year. This project launch since 2013 but yet to complete till today 2024. Now become a sick project.
Show more
1 Like · 8 months · translate
Eddy Gan
RM 15 million equivalent to 3 cents per share. This is the reason company need to pay THE PEAK condominium buyers due to project delay instead of give shareholders dividend.
Like · 8 months · translate
Eddy Gan
E'Island Puchong project also delayed. Project launch on 2019 & expected complete on Q3 2023 but now delayed to Q3 2024. Is it another penalty need to pay due to delay?