It is not about other project first , it is about Tcs current financial position not allowed to fail even 1 project .court case . Image damage , over 150m to 200m refund back to buyer and Need destroy the building and rebuild , maybe cannot rebuild condo anymore at the area , as basement not done well , may change to 3-4 storey shoplot at the end .
You think too much bro. Refund is developer issue. TCS is just doing main building job. Except piling. Construction company is the most hard job. If developer can build condo, they already do it. At the end, they can’t build. Dato IR Tee Chai Seng have lot experience for construction building. You think KLK, Sime properties, Spsetia and other developer blind.
your are too naive , developer will claim those who responsible . And sue the main con too at the end . And the end , main con and developer both kena , main con is the one get hit the most , as agreement and term and confirm and it is inside law contract .These kind of crack , it may be base not doing well , if you have basic construction knowledge you won’t say what you saying . Let see and find out soon. Please more knowledge full . And Tcs won’t getting any paid too at the end. Which many millions cost occurred too .
they can claim contractor allowance risks / CARS insurance. but, no profits. subject to the independent engineer report. speculation:
- engineer under design which unlikely to be the case
- IOW sleep or took bribes and the contractor workers reduce rebar or use lower grade concrete or steel works.
- workers didn't execute works according to method statement
- design not according to wind tunnel test
Nothing To do With normal Worker , the company top management have To Check QC And approve before can built next level Or nect stage , And company bind the resposible . Yes , let them investigate.